Archtop Fiber Falls Below Half of 250,000-Home Plan as Permits Stretch to 600 Days
Updated
Updated · The Daily Freeman · Aug 3

Archtop Fiber Falls Below Half of 250,000-Home Plan as Permits Stretch to 600 Days

1 articles · Updated · The Daily Freeman · Aug 3

Summary

  • Less than half of Archtop Fiber’s planned 250,000-home buildout is complete, the company said, leaving its Hudson Valley expansion significantly behind schedule despite more than 20,000 customers already connected.
  • 500-to-600-day utility permit cycles—versus the 115 days Archtop expected—are driving the delays, with Central Hudson reviews, National Grid approvals and state DOT right-of-way signoffs slowing both pole and underground work.
  • $100,000 to $150,000 a mile in some utility-related construction costs, plus millions of dollars of fiber sitting in warehouses, have made sparse service areas especially hard to build economically.
  • Archtop began building in 2023 in Kingston, Warwick, Germantown, Saugerties and Red Hook, but expansion into Ulster, Esopus, Hurley, Woodstock, Rhinebeck, Catskill, Stockport and Hudson has produced mixed results.
  • The company said it is still hiring, using acquired local phone-company infrastructure and prioritizing areas municipalities identify as most in need when new grants become available.