Lahaina Rebuild Still Lags With 2 Commercial Permits as Delays Stall Dozens More
Updated
Updated · Maui News · Aug 6

Lahaina Rebuild Still Lags With 2 Commercial Permits as Delays Stall Dozens More

1 articles · Updated · Maui News · Aug 6

Summary

  • Two commercial permits and one completed project were cited at a July 1 Lahaina meeting as proof rebuilding is on track, but the visible progress is thinner than officials suggested.
  • One completed permit covered only site work and a concrete pad at a gas station, while another same-day approval went to a restaurant built in 2022 that qualified for a fast-track reuse of recent permits.
  • Dozens of other commercial rebuilds remain stuck in permitting, slowed by unclear documentation, public hearings, shoreline Special Management Area rules and lengthy historic reviews.
  • State Historic Preservation Division demands have stretched some cases for nearly a year or more; one Front Street project waited from July 2025 to June 2026 for survey clearance.
  • Costs rise by about $100 to $200 a day per delayed permit, and despite recent state streamlining laws and a 90-day review deadline, the report argues broader executive action is still needed.