$6.964 billion in planned Air Force spending would remake Joint Base Elmendorf-Richardson through 2035, with about $2.066 billion tied to the first Fightertown tranche in fiscal 2027.
The project would replace or expand hangars, dorms, taxiways, fuel and munitions storage, and other flight-line infrastructure because existing facilities no longer meet mission needs.
Military officials want construction to start next summer and are using faster contracting tools, including Other Transaction Authority and progressive design-build, to avoid slower standard procurement rules.
Anchorage officials and businesses are preparing for an influx of construction work and military personnel, even as housing is already tight with 98% of JBER family units occupied.
Sen. Dan Sullivan said the buildup reflects U.S. concern about Russia and especially China, though the defense bill funding the first tranche still awaits full congressional approval.