Energy Transfer Reroutes 17.8-Mile Gas Pipeline for Oracle-OpenAI Data Center After Rejection
Updated
Updated · Bloomberg · Aug 18

Energy Transfer Reroutes 17.8-Mile Gas Pipeline for Oracle-OpenAI Data Center After Rejection

3 articles · Updated · Bloomberg · Aug 18

Summary

  • Energy Transfer has redrawn the route for a 17.8-mile natural gas pipeline meant to supply power to a large Oracle-OpenAI AI data center.
  • The change follows New Mexico regulators’ rejection of an earlier pipeline plan, forcing the company to seek a new path.
  • Under the revised proposal, Energy Transfer wants to build part of the conduit on land managed by the US Bureau of Land Management.
  • The reroute shows how permitting hurdles are shaping infrastructure plans tied to the heavy energy demands of AI data centers.