  • Beale Infrastructure is continuing construction of its 600-megawatt Project Blue campus near Tucson even after the City Council unanimously blocked annexation that opponents thought would kill the deal.
  • 31 million gallons of groundwater a year were approved for two on-site wells to support construction, while Beale says the operating facility will use closed-loop air cooling and only limited domestic water.
  • Opposition has swelled from packed public meetings to lawsuits, protests and permit challenges, with activists citing Arizona’s shrinking Colorado River supply, heat-island effects and fears of higher power bills.
  • Pima County sold the 290-acre site to Beale for about $20 million after touting 3,000 construction jobs, 200 permanent jobs and $152 million in decade-long tax revenue, but Tucson later imposed strict new rules and the county adopted a 120-day moratorium on new data centers.
  • The fight reflects a broader Arizona split: leaders embraced TSMC’s water-intensive chip expansion for its jobs and supplier ecosystem, while newer hyperscale data centers face bipartisan backlash over whether scarce desert water should support AI infrastructure.

Insights

Why is Arizona embracing TSMC’s water-hungry fabs while fighting data centers that promise billions in investment?
If data centers create fewer jobs but strain water and power, what should Arizona demand before approving another mega-campus?