Anthropic Buys $3.4 Billion of Caterpillar Turbines as AI Power Shortage Deepens
Updated
Updated · TechCrunch · Nov 9
Anthropic Buys $3.4 Billion of Caterpillar Turbines as AI Power Shortage Deepens
1 articles · Updated · TechCrunch · Nov 9
Summary
$3.4 billion will buy Anthropic up to 1.7 gigawatts of Caterpillar natural-gas generation, a rare infrastructure purchase for a company that has typically rented compute capacity.
Anthropic moved as turbine backlogs stretch into the early 2030s and grid-connection queues are similarly long, making secured power capacity increasingly hard to obtain.
The generators were originally ordered by supplier OnePWR, which could not complete the purchase; Anthropic had planned to buy through OnePWR before going directly to Caterpillar.
The shift contrasts with Anthropic’s May S-1, which disclosed a $1.25 billion-a-month deal with xAI through May 2029 and signaled more service contracts rather than owned infrastructure.
Anthropic joins Google, Amazon, Microsoft and Meta in turning to on-site gas power, a buildout that could push U.S. data-center gas demand above Germany and Japan combined by 2035.